| MILESTONE | SCHEDULE |
| File FERC Section 7(c) Application and Environmental Report | July 2011 |
| Receive FERC Certificate of Public Convenience and Necessity | January - February 2012 |
| Commence Site Work and Compressor Station Construction upon receipt of FERC authorization | March - April 2012 |
| Place Project Facilities into Service | November 2012 |