Proposed Construction Schedule

MILESTONE SCHEDULE
 File FERC Section 7(c) Application and Environmental Report July 2011
 Receive FERC Certificate of Public Convenience and Necessity January - February 2012
 Commence Site Work and Compressor Station Construction upon receipt of FERC authorization March - April 2012
 Place Project Facilities into Service November 2012